Math, asked by LornetCornwall, 1 year ago

245 workersbwould take 93 days to build a market .Only 217 have been employed .How many days would it actually take?

Answers

Answered by rathibhagwati3
2

Answer:


Step-by-step explanation:


Attachments:

LornetCornwall: Thank you so much now i understand
shambhu1045: ok
shambhu1045: read agarawal rs book
Answered by shambhu1045
1
(217×93)/245=105. 105 days