25 labourers can complete a building in 8 months. how many labourers will be required to construct another building of triple size as that of previous building in 10 months?

Answers

Answered by Trendy
0
60 no of labourers required

Trendy: if correct mark branliest please
maroof1: plz explain the steps
Trendy: let take the work done in second building as triple of first building
Trendy: than also triple the time that is 24 month
Trendy: now multiply 24*25and divide with the given time that is 10 months
Trendy: you gonna get your answer
Trendy: hope you understand
Answered by sushmita24
1
I think 16 numbers are laboratory required in this sum