25 men
can complete a work in 16
day 5 men left the work
after 10 days
in how many day will the remaining work will be completed
Answers
Answer:
6 days
Step-by-step explanation:
15 men can do the work in 12days.
After 4 days remains work of 8days.
If 15 men can do that in (12-4) 8 days
Then 1 man can do in 15x8= 120 days. After 4days 5 more men joins the work
So total (15+5) 20 men can do the rest work (120÷20)= 6 days. Ans.