25 men works 5hr/ day to complete a work in 12 days then how many men is required to complete it in 18 days
Answers
Answered by
0
Step-by-step explanation:
No. of workers = 25
Time Taken = 12 days
No. of workers required for completing the work in 1 day = 12 × 25
No. of workers required for completing the task in 18 days = 12 × 25 / 18 = 16.66 = 17 (rounding off)
Hence, 17 workers are required.
Answered by
0
i think u using this formula and got the ans.
M1×D1×W1. = M2 × D2× W2
Step-by-step explanation:
WHERE
men =m1 and m2
d = day
w =work