Ram and Sham can do a work in 6 and 12 days respectively. Ram starts
the work and Sham joins after 3 days to finish the work together. For
how many days Sham worked?
A) 6 days
B) 5 days
C) 2 days
D) none of these​

Answers

Answered by rranjitkumar887760
0

Answer:

answer. B hoga.

aur koi question ho to batana

Answered by juhi3963
0

Answer:

Answer is B

Step-by-step explanation:

Any more questions, please say. If the answer is right then give feedback