Math, asked by balikakonkale5447, 10 months ago

270 men were to finish a piece of work in 14 days but some men fell sick and the remaining men could complete the work in 21 days how many men fell sick

Answers

Answered by pagraju1
1

Answer:

35 people fell sic

Step-by-step explanation:

Answered by worldgaming323
6

Answer:

90 Men Fell Sick

Step-by-step explanation:

270 men were supposed to finish a piece of work in 14 days.

1 man would have taken (270 x 14) = 3 780 days

However, some fell sick and the rest took 21 days to complete the piece of work

If y men fell sick, (270 - y) men were left.

(270 - y) men took 21 days to finish a piece of work.

3 780 = (270 - y)(21) => 270 - y = 3 780/21 = 180 => y = 90.

90 men fell sick