270 mens were to finish a piece of work in 14 days . but some man fell sick and the remaining man could help the work in 21 days how many men fell sick .

please answer my question I will make you brainliest .

Answers

Answered by tishtha0902007
5

hope so it will help you

Attachments:
Answered by lalakamil125
4

Answer:

405 mens

Step-by-step explanation:

14days___270 men

21days____? men

21÷14×270

3÷2×270

3×135

=405