28 children can do a piece of work in 50 days.How many children are needed to complete the work in 30 days?

a. 49

b. 40

c. 35

d. 45

Answers

Answered by Anonymous
0
HEY DEAR ...

we know work=persons*days;
here work is same in both cases w1=w2;
28*50=p*30
p=45 approximately

HOPE , IT HELPS ...