3.6 men can do a piece of work in 12 days.
i) In how many days would 1 man do the
same work?
ii)In how many days would 8 men do the
same work?
Answers
Answered by
11
Proportion
We know that :
If the number of men ( M ) increases to do a piece of work then at the same time number of days ( D ) taken to complete the work will decrease.
Hence, number of men is inversely proportional to number of days.
⇒ M ∝ 1 / D
⇒ M × D = Constant
⇒ M₁D₁ = M₂D₂
Case 1 :
6 men can do a piece of work in 12 days. Number of days taken by 1 man = ?
Here :
- M₁ = 6
- D₁ = 12
- M₂ = 1
- D₂ = ?
Now using the formula given above
⇒ M₁D₁ = M₂D₂
⇒ 6 × 12 = 1 × D₂
⇒ 72 = D₂
Therefore 1 man can do the same work in 72 days.
Case 2 :
6 men can do a piece of work in 12 days. Number of days taken by 8 men = ?
Here :
- M₁ = 6
- D₁ = 12
- M₂ = 8
- D₂ = ?
Now using the formula given above
⇒ M₁D₁ = M₂D₂
⇒ 6 × 12 = 8 × D₂
⇒ 72/8 = D₂
⇒ D₂ = 9
Therefore 8 men can do the same work in 9 days.