3. A and B can do a piece of work in 15 days and A and C can do it in 10 days. they started working together. After 3 days B left the work and one day later A also left.The remaining work was finished by C in 11 days. The work can be finished by A,B and C together in how many days?
Answers
Answered by
0
Answer:
7 days..........................