3. In CBR test the value of CBR is
calculated at
A.
2.5 mm penetration only
B. 5.0 mm penetration only
C. • 7.5 mm penetration only
D. both 2.5 mm and 5.0 mm
penetrations
Answers
Answered by
0
Answer:
(D) both 2.5 mm and 5.0 mm penetrations