3 men and 4 boys can complete a piece of work in 12 days. 4 men and 3 boys can do the same work in 10 days. Then 2 men and 3 boys can finish the work in?
Answers
Answered by
1
Answer:
(3men+4boys)12 days
= (4men+3boys) 10 days
18men+24boys=20men+15boys
2 men = 9 boys..............(i)
4men+3boys=(2×9)boys+3boys=21boys
21 boys can do a work in 10 days
Total work = 21×10=210 units
2 men + 3 boys = 9 boys + 3 boys (from eq i)
= 12 boys
12 boys can do 210 units in
21012=352=1712 days