3 men or 4 women or 6 children can do a work in 12 days. Now, 2 children and 1 men
can complete the work in ?
Answers
ans=18 days
Step-by-step explanation:
3 men = 6 children
1 men= 6/3=2 children
therefore, 2 children +1men=2 children+2 children
= 4 children
now, 6 children can complete a work in=12 days
so, 1 child can complete a work in=12×6= 72 days
therefore, 4 children can complete a work in= 72/4= 18 days
conclusion: two children and one men can complete a work in 18 days. (ANS.)
PLEASE MARK ME AS BRAINLIEST
Answer:
2 children and 1 man can complete the work in 18 days.
Step-by-step explanation:
3 men can complete the work in 12 days.
6 children can complete the work in 12 days.
Therefore, 3 men is equivalent to 6 children
3 men = 6 children
1 men = children
1 men = 2 children
Since 2 children and 1 man have to complete the work.
Therefore, 2 children and 1 man is equivalent to 2 children.
Now,
6 children can complete the work in 12 days
1 child can complete the work in 12 × 6 days
1 child can complete the work in 72 days
4 children can complete the work in days
4 children can complete the work in 18 days.
Therefore, 4 children which are also equivalent to 2 children and 1 man, can complete the work in 18 days.