3 men or 8 boys can do a piece of work in 17 days.how many days will 2 men and 6 boys together take to finish the same work
Answers
Answered by
12
3 men = 8 boys
1 man = (8/3)boys
2 men + 6 boys = (16/3)boys + 6 boys = (34/3)boys
8 boys can do a piece of work in 17 days
(34/3)boys can do the same work in (17*8*3)/34 days = 12 days
your answer is 12
hope you like it
1 man = (8/3)boys
2 men + 6 boys = (16/3)boys + 6 boys = (34/3)boys
8 boys can do a piece of work in 17 days
(34/3)boys can do the same work in (17*8*3)/34 days = 12 days
your answer is 12
hope you like it
sakshi8918:
hi
Answered by
4
Answer:
Step-by-step explanation:
8 boys = 17 days
1 boy = 17/8 = 2.125 = 2 days
3 men = 17 days
1 man = 5.67 = 6 days
(5.67 x 2) + (2.125 x 6) = 24.09 Days= 24 days