3 punjabis can complete a job in 6 days. 5 kashmiris can complete the same job in 18 days. In how many days will 4 punjabis and 10 kashmiris together complete the job
Answers
Answered by
3
Answer:
Step-by-step explanation:
Number of days taken by 3punjabi to complete the work= 6days
Number of day taken by each Punjabi=6/3=2 days
No. Of days taken by 5 kashmiri to complete the work=18days
No.of days taken by each kashmiri=18÷5=3.6days
No. Day four Punjabi will take=4×2=8 days
No.of days 10 kashmiri will take =10×3.6=36days
Total no. Of days taken by both=8+36=44days