Math, asked by ashmitabiswas0719, 9 months ago

3 women or 5 girls take 17 days to complete a piece of work, how long will
7 women and 11 girls working together take to complete the work?​

Answers

Answered by mohinismahajan
10

Answer:

given work done by 3 women= work done by 5 girls

work doe by 1 women= work done by 5/3 girls

therefore work done by 7 women and 11 girls= work done by 35/3+11= 68/3 (girls)

since 5 girls can complete the work in 17 days so 1 girl can complete in 85 days then 7 women and 11 girls can complete the work in= 85/68/3=3 3/4 days.

or

since 3 women work= 5 girls work

1 women's work= 5 girls work

hence, 7 women's work= 5/3*7= 35/3

7 women's and 11 girls work= 35/3+11

= 35+33/ 3= 68/3

since 5 girls can do the work in 17 days,

hence, 1 girl can do the work in ( 17*5 days)= 85 days

hence, 68/3 girls can do the work in 85/68/3 days= 85*3/68= 255/68= 15/4

= 3 3/4 days

pls mark it as the brainliest

hope it helps