30 men build wall in 10 days. 1 man will takr how many days to build a wall

Answers

Answered by vikyrajdeka8987
1

Answer:3 men take 10 days to build the wall, which is a total of 30 manned days.

3men∗10days=30totalmanneddays

So 1 man would build the wall in the span of 30 days. Which means 2 men would cut the days in half, giving you a total of 15 days.

30mandays/2men=15days

It would take 2 men 15 days to build the wall,

Step-by-step explanation:as if is not been understood so