30 men can reap a field in 16 days. how many men will ne required to reap another field which is triple in size within 15 days
Answers
Answered by
10
Answer:
Step-by-step explanation:
96 men will be required to reap another field which is triple in size within 15 days.
Answered by
4
96 men will be required to reap another field which is triple in size within 15 days
hope it helps you ✌️