30 men working 5 hours a day can do task in 16 days
Answers
Answered by
7
Answer:
If 30 men work 5 hours a day for 16 days,then we can say that 30 men worked for total (5x16) 80 hours. Therefore it took (30x80) 2400 man-hours to complete the task.
Now we have 40 men available, ready to work for 6 hours a day. Therefore
40x6xno of days =2400 man hours
No of days=10.
Answered by
1
Answer:
plz plz plz Mark me brainliest