30 women can finish a piece of work in 20 days how many women will be needed to finish it in 12days

Answers

Answered by Jiyakhera
0
WOMEN. DAYS
30. 20
? 12
As no. of days has been decreased
so no. of of women will be increased...
equation arrives.....
30*20=12x
600=12x
50=x
Hope it helps... :)
Hope you are known with this proportion method...
Answered by Ompanda
0
let =x=30 women
y=20 women
x¹=?
y=12
x×y=x¹×y¹
30×20=x¹×12
x¹=30×20/12
x¹=50 women