Math, asked by superfriendTwin, 1 year ago

32 men can finish a work in 24 days how many men can finish the same work in 16 days

The answer is 48 days
I want process


JainamKapasi: 48 mens can finish work in 16 days

Answers

Answered by siddhartharao77
29
The Number of days taken by 32 men = 24 days.

The Number of days taken by x men = 16days.

x * 16 = 32 * 24

x = 32 * 24/16

x = 768/16

x = 48.


Therefore 48 men can finish the work in 16 days.


Hope this helps!

superfriendTwin: thanks
siddhartharao77: :-))
Answered by ravi271
25
it is a direct and inverse qeustion
and it is a inverse variation
so according to the question
32 \times 24 = 16 \times x \\ 32 \times 24 = 16x \\  \frac{32 \times 24}{16}  = x \\ 48 = x
So 48 men can do this work in 16 days

superfriendTwin: Thanks
Muddasir1: excellent