35 men could do a certain work in 40 days. If after 4 days, 7 of the men suddenly left, in how many days will the REMAINING work be completed?
Please help with the answer
Answers
Answer:
44 days
Step-by-step explanation:
35men=40 days
1 man=1440 days
28 men=50 days
After 4 days the remaing work will be done in 44 days.
Given data : 35 men could do a certain work in 40 days. After 4 days, 7 of the men suddenly left.
To find : In how many days will the REMAINING work be completed?
Solution : Now, a/c to given data;
- 35 men can do a work in 40 days
Hence,
- 35 men's 1 day's work = 1/40
and
- 1 men's 1 day's work = 1/(40 * 35)
Now,
- 35 men's 4 day's work = (1/40) * 4 = 4/40 = 1/10
Here, we have to find out remaining work after 4 day's, So,
- Remaining work = complete work - 35 men's 4 day's work
- Remaining work = 1 - (1/10) = (10 - 1)/10 = 9/10
Here, we know that, after 4 days, 7 of the men suddenly left the work, so
- Total men left = 35 - 7 = 28 men
Now,
- 28 men's 1 day's work = (1/40 * 35 ) * 28
- 28 men's 1 day's work = 28/(40 * 35)
- 28 men's 1 day's work = 28/1400
- 28 men's 1 day's work = 1/50
Therefore, 28 men's can do 1/50 in 1 day.
Now,
➜ Time taken by men's to complete work = (Remaining work)/(28 men's 1 day's work)
➜ Time taken by men's to complete work = (9/10)/(1/50)
➜ Time taken by men's to complete work = (9/10) * 50
➜ Time taken by men's to complete work = 9 * 5
➜ Time taken by men's to complete work = 45 days
Answer : Hence, the remaining work will be completed in 45 days.