36 heads of people of certain village can construct 120 meters of road working 6 hours daily in 12 days. Another 6 heads of people are involved
in this work and the duration of work of each day is increased by 2 hours. Find the length of the road to be constructed in 9 days.
Pls answer fast with statement explaination.
here,'heads of people' refers to many people working together.

Answers

Answered by Manjula29
10

​According the sum,

36 people were started to work.

6 person were added. so new number of workers = (36+6) 42

starting working hours was 6 hr/ day

2 hrs increased, so they have to work 8 hrs/day.

In the beginning people worked for 12 days,

after increasing heads ,people worked 9days.

there fore total number of people=

120×42/36×8/6×9/12

= 140 men

Ans:- Here total 140 people were working together.