Math, asked by Srishanth8th, 1 year ago

36 men can do a piece of work in 12 days . In how many days 9 men can do the same work

Answers

Answered by cleanly
5
since,36 man do a piece of work in 12day
so, 1 ----------------------------------12X36 day
so, 9 --------------------------------12X36/9
=48 days

Srishanth8th: is it correct ?
11Adi: Ya it is correct