360 worker can finish a construction work in 60 days how many more workers should be added to complete the same work in 45 days?​

Answers

Answered by hemlatanain1941
21

Answer:

480 WORKERS

Explanation:

360×60=45×X

(360×60)÷45=X

360÷45=8

8×60=X

480=X

ANSWER =480 WORKERS

I HOPE THAT YOU LIKE THIS ANSWER.