360 workers can build a wall in 80 days . how many workes will be required to do same work in 40days
pls... tell me fast exam
Answers
Answered by
1
Answer:
280
this is your answer please mark me as brainliest I am requesting you
Answered by
0
no . of workers required to build the wall in 80 days = 360
no . of workers required to build the wall in 1 day= 360×80=2880
no. of workers required to build the wall in 40 days = 2880÷40=720 (ans)