3m and 4w can complete a work in 16 days while 4m and 3w can complete the same work in 12 days. Then find 7m and 7w can complete same work in how many days?
Answers
. I will use Unitary Method to solve this question.
We are given that 3 men do the work in 16 days.
So, Work done by 3 men in 1 day =1/16
Now, Work done by 1 man in 1 day = 1/(16∗3)=1/48 days.
Similarly, Work done by 1 woman in 1 day can be found out and it is 1/64
Now, Work done by 12 men in 1 day = 12/48=1/4
Work done by 8 women in 1 day = 8/64=1/8 .
Now, Work done 12 men and 8 women in 1 day = 1/4+1/8=3/8
So, 12 men and 8 men do 3/8 of work in 1 day.
So, to complete the work, it will take them 8/3 days. We Just inverse the fraction found above. This is the beauty of Unitary Method.
So, the total time taken is 8/3 days = 2 Days 16 Hrs
Hope that helps. :)
Answer:
3m + 4w - 16 days
4m + 3w - 12 days
so, (3m + 4w) 16= (4m + 3w) 12
48m + 64w = 48m + 36w
28w= 0
therefore w = 0
so (3m + 0) 16= (4m + 0) 12
3 men can complete the work in 16 days
total work = 3×16= 48 unit
Hence 7m +7w = 7m + 0
so, 7m + 7w can complete the work in 48/7 days.