4. A and B can do a piece of work in 30
days, B and C can do it in 40 days and C
and A can do it in 60 days. In how many
days A, B and C can finish the work
together?
Answers
Answered by
1
Answer:
Step-by-step explanation:
A + B = 30 days
B + C = 40 days
C + A = 60 days
Let's take totak work as LCM of 30,40 and 60 = 120 units
Their unit work in a day will be
A + B = 120/30 = 4 units/day
B + C = 120/40 = 3 units/day
C + A = 120/60 = 2 units/day
Add these equations
2A + 2B + 2C = 4+3+2
2(A + B + C) = 9
A + B + C = 9/2 units per day
Therefore to complete 120 units they'll take a time of
= 120/(9/2)
= 120*2/9 = 40*2/3
= 80/3 days (Ans)
Or 26,2/3 days (mixed fraction format)