4. A can do a work in 6 days and B can do it in 8 days. They worked together for 2 days
and then B left the work. How many days will A require to finish the work?
Answers
Answered by
4
Answer:
Step-by-step explanation:
A in one day=1/6
B=1/8
They worked together for two days so total work=2/8+2/6=7/12
Remaining work=1-7/12
=5/12
Time required for A to do 5/12 work=1/6 divided by 5/12
=5/2
So 5/2 days are required