Math, asked by lisishivlal2006, 5 months ago

4. A contractor undertakes to dig a canal,
6 kilometre long, in 35 days and employed
90 men. He finds that after 20 days only 2 km
of canal have been dug. How many more men
must he employ to finish the work in time?​

Answers

Answered by haritha45
6

Length of canal = 6 km

Length of canal = 6 kmIn 20 days canal made = 2 km

Length of canal = 6 kmIn 20 days canal made = 2 kmRemaining length of canal = 6 – 2 = 4 km

Length of canal = 6 kmIn 20 days canal made = 2 kmRemaining length of canal = 6 – 2 = 4 kmRemaining time = 35 – 20 = 15 days

In 20 days 2 km canal is made by = 90 men

In 20 days 2 km canal is made by = 90 menIn 1 day 2 km canal is made by = 90 x 20 men

In 20 days 2 km canal is made by = 90 men

In 20 days 2 km canal is made by = 90 menIn 1 day 2 km canal is made by = 90 x 20 men

In 15 days 2 km canal is made by = (90 × 20)/15 men

In 15 days 2 km canal is made by = (90 × 20)/15 menIn 15 days 1 km canal is made by = (90 × 20)/(15 × 2) men

In 15 days 4 km canal is made by = (90 × 20 × 4)/(15 × 2) men = 6 x 10 x 4 men = 240 men

Number of more men to be employed to finish the work in time = 240-90 = 150 men

Answered by stelladaniel216
6

Answer:

The solution to the problem is illustrated in the picture attached.

Step-by-step explanation:

Refer the picture for the step-by-step explanation.

Attachments:
Similar questions