4. If 10 workers finish the
construction of a bunglow in 153
days, then how many days will 17
workers need?
O 91 days
O 90 days
ОО
89 days
Answers
Answered by
0
Answer:
90 days
Step-by-step explanation:
Suppose
needed days= x
Ratio.
days. : worker
153:x. : 10:17
x/153= 10/17
x=10/17*153
x=1530/17
x=90