4. If 65 men can do a certain piece of work in 28 days, how long will 35 men take to do the same piece of work?
Answers
Answered by
5
Step-by-step explanation:
65 men = 28 days
1 men = 28/65 days.
35 men = 28/65 × 35 days.
=>>>
Therefore answer is 15 days.