Math, asked by supriyabanskota, 3 months ago

4 machines of a factory can finish the required amount of production in 6 days.
If one machine had machinery defect and stopped functioning, in how many
days would the remaining machines finish the same quantity of production at
the same rate of production?​

Answers

Answered by ahteshamszahid
1

4/3=6/x

1.367x=6

X=6/1.367

x=4.389 days