Math, asked by surendramaha98, 1 year ago

4 men and 6 women can finish in work in 16 days in how many days in some work incomplete by 2 men in 9 women​

Answers

Answered by singhmegha363
1

Answer:

4 men can finish a work in 16 days OR 6 women can finish a work in 16 days. 4 men can finish a work in 16 days => 1 man does a work in 64 days. 6 women take 16 days => 1 woman takes 96 days. 2 men and 9 women can complete 2(1/64) + 9(1/96) = (1/32) + (3/32) = (1/8) of work in 1 day.

Step-by-step explanation: