4 men can repair a road in 7 hours. How many men are required to repair the road in 2 hours ?​

Answers

Answered by BRAINLYARMY001
3

Answer:

hi

your answer is here !

Step-by-step explanation:

M x T / W = Constant

where, M= Men (no. of men)

T= Time taken

W= Work load

So, here we apply

M1 x T1/ W1 = M2 x T2 / W2

Given that,

M1 = 4 men,

T1 = 7 hours ; T2 = 2 hours,

we have to find M2 =?

Note that here,

W1 = W2 = 1 road, ie. equal work load.

Clearly, substituting in the above equation we get,

M2 = 14 men.

follow \:  \:  \: me

Answered by sharmaarun612014
1

Answer:

14 men

Step-by-step explanation: