4 men can repair a road in 7 hours. How many men are required to repair the road in 2 hours ?
Answers
Answered by
3
Answer:
hi
your answer is here !
Step-by-step explanation:
M x T / W = Constant
where, M= Men (no. of men)
T= Time taken
W= Work load
So, here we apply
M1 x T1/ W1 = M2 x T2 / W2
Given that,
M1 = 4 men,
T1 = 7 hours ; T2 = 2 hours,
we have to find M2 =?
Note that here,
W1 = W2 = 1 road, ie. equal work load.
Clearly, substituting in the above equation we get,
M2 = 14 men.
Answered by
1
Answer:
14 men