4 men or 6 boys or 8 girls can perform a piece of work in 15 days. How much time 9 men, 12
boys and 8 girls take to do the same work?
Answers
Answered by
0
Answer:
20/7 Days
Step-by-step explanation:
Step 1:
According to question,
4 men = 6 boys = 8 girls
4 men = 6 boys
4 men = 8 girls
Step 2:
9 men+12 boys+8 girls=(9+8+4)= 21 men
Step 3:
4 men can do a piece of work in 15 days
21 men can do a piece of work in
=(15*4)/21
=20/7days