4 men or 6 women complete a job in 30 days.
How much time will -12 women and 2 men
take to complete the same work.


give complete explanation

Answers

Answered by gangulysona050976
2

Answer:

12 days

Step-by-step explanation:

4 men=30 days

And

6 women=30 days

Thus, 4 men =6 women

2 men=3 women

Now 12 women+ 2men=15women

We know that,

6 women take=30 days

Thus,15 women take=(30*6)/15days

=12 days