4. Mohan does 25% more work than sohan. If Sohan can do it in 20 days, then
(a) In how much days will mohan alone finish the work? (b) working together
in how many days Mohan and Sohan will finish it?

Answers

Answered by arunkumar2290
1

Answer:

20×25/100=20×1/4=5

20days-5days=15days

Answered by sunilrashmi46
1

1) In 15 days

2)In 8 4/7 days