4 soldier can dig a trench in 5 days in how many days 10 soldier do this job
Answers
Answered by
3
Answer:
2
Step-by-step explanation:
4soldier = 5 days
10 soldiers = x days
By cross multiplication
10x = 4 × 5
10x = 20
x = 20/10
x = 2 days
Answered by
2
Answer:
2 days
Step-by-step explanation:
1 soldier can dig in5*4 = 20 days
10 soldiers can dig in 20/10 = 2 days