4 typist are employed to complete a work 12 days.If 2 more typist are added they'll finish the work in how many days?​

Answers

Answered by rishikeshdas525
6

Answer:

Step-by-step explanation:6 typist

will take 8 days to complete the work

Answered by rishabhpy3
6

Answer:

Pls mark as brainliest

Let the days they will take be x.

So,

4 : 12 :: 4 + 2 : x

As, this an indirect proportion, we will use x:y :: y : x = xy = yx

48 = 6x

x = 48 / 6

x = 8