4 typist are employed to complete a work 12 days.If 2 more typist are added they'll finish the work in how many days?
Answers
Answered by
6
Answer:
Step-by-step explanation:6 typist
will take 8 days to complete the work
Answered by
6
Answer:
Pls mark as brainliest
Let the days they will take be x.
So,
4 : 12 :: 4 + 2 : x
As, this an indirect proportion, we will use x:y :: y : x = xy = yx
48 = 6x
x = 48 / 6
x = 8