4 worker can make a wall in 10 days . how many more workers will be needed to make wall in 5 days​

Answers

Answered by btmp46
0

Answer:

eight members needed

Step-by-step explanation:

Total no of workes to make a wall in 10days=4

no of workes needs to build

the wall in 5 days. = 4*2

=8