4 workers can build a house in 88 days . How many days will 11 workers take to build a similar house?
Answers
Answered by
6
Answer:4:88::11:x
4x=80*11
x=(80*11)/4
x=20*11
x=242 days
Step-by-step explanation:
Answered by
10
Answer:
32 days
Step-by-step explanation:
This question is based on INVERSE VARIATION.
This means that More the Workers, Lesser the Days & Lesser the Workers, More the Days.
4 workers ------------- 88 days
4×88 workers ------------- 1 day
11 workers ------------- [4×88×1] ÷ 11
32 days ←ANSWER
PLEASE MARK IT AS THE BRAINLIEST!!!!!