40 men can complete a piece of work in 40 days. They
started the work together. But at the end of each 10th
day, 5 men left the job. The work would have been
completed in??!
Answers
Answered by
4
Answer:
Let a man can do 1 unit / day.
Total work = 40 men ×40 days
= 1600 units
40 men can do the work in 10 days
= 400 units
According to question,
{ 5 men left after to days }
35 men can do the work in 10 days
= 350 units
30 men can do the work in 10 days
= 300
25 men can do the work in 10 days
= 250
20 men can do the work in 10 days
=200
men left 20 - 5 = 15 and
work left = 1600-1500 = 100 unit
They will complete in 100/15 = 6 2/3 days
Total days = 50 + 6 2/3 = 56 2/3 days.
Hope it's Help You ❇
Answered by
2
Let a man can do 1 unit/ day.
Total work = 40men×40days
= 1600 units
40 men can do the work in 10 days
= 400 units
According to question,
(5men left after 10 days)
35 men can do the work in 10 days
= 35×10
= 350 units
30 men can do tlhe work in 10 days
=30×10
=300
25 men can do the work in 10 days
=25×10
=250
20 men can do the work in 10 days
=20×10
=200
men left 20−5=15 and
work left = 1600−1500=100 units
they will complete in
=100/15
=20/3 days
Total days = 50+20/3
= 56 2/3 days
I hope that this answer will help you.✌✌Like it and mark me on brainliest❤❤