40 men can cut 70 trees in 8 hours. If 8 men leaves the job. How many trees will be cut in 12 hours.
Answers
Answered by
1
Answer:
84
Step-by-step explanation:
Total men = 40.
Given that 8 men leaves the job.
Men left = 40 - 8
= 32.
Now,
⇒ 40 * 8 * W₂ = 32 * 12 * 70
⇒ 320 * W₂ = 26880
⇒ W₂ = 26880/320
⇒ W₂ = 84.
Therefore, 84 trees will be cutted in 12 hours.
Hope it helps!
jatinboss:
i think 72 trees will be cut down
Answered by
1
40 men can cut 70 trees in 8 hours
1 men can cut 70/40 trees in 8 hours
40-8
=32 men can cut 70×32/40 trees in 8 hours
32 men can cut 70×32/(40×8) trees in 1 hours
32 men can cut in 12 hours 70×32×12/(40×8)= 84 trees
............Hope It Helps YOU..................