40 men can do a piece of work in a given time. if only 30 men can be engaged, 6 more days are needed to complete the given work. in how many days can 60 men do the work
Answers
Total work=40x
For 30 men, 6 more days required. So, total work= 30×(x+6)=30x+180.
Therefore, 40x=30x+180
Implies 10x =180
X=18. Total work=40x=40×18
For 60 men, days= (40×18)÷60
= 12 days.
Answer:
can do the same work in days.
Step-by-step explanation:
Given:-
men can do a piece of work in a given time.
Only 30 men is engaged, 6 more days are needed to complete the given work.
To find:-
The number of days can 60 men do the work.
Step 1 of 1
Let us suppose that 40 men can do a piece of work in x days.
According to the question,
If only 30 men can do the work then 6 more days are needed to complete the given work, i.e.,
The numbers of days in which 30 men can do the same piece of work is,
=
Since 6 more days are needed.
So, the equation becomes,
= x + 6
Cross-multiply the equation as follows:
40x = 30(x + 6)
40x = 30x + 180
4x = 3x + 18
4x - 3x = 18
x = 18
This implies 30 men can do the same piece of work in 18 days.
Now,
can do the same work =
= 12 days
Therefore, 60 men can do the same work in 12 days.
#SPJ3