40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in ¾ of the time. find the ratio of number of new men to number of old men.
Answers
Answered by
6
Find the number days needed to complete the work when more men were needed:
Number of days = 3/4 x 28 = 21 days
40 men took 28 days (Given)
⇒28 days = 40 men
Find number of men needed for the job to be completed in 1 day:
28 days = 40 men
1 day = 40 x 28 = 1120 men
Find number of men needed for the job to be completed in 21 day:
1 day = 1120 men
21 days = 1120 ÷ 21 = 160/3 = 53 1/3 men
Find the addition of men:
53 1/3 - 40 = 13 1/3 = 40/3
Find the ratio of old men : new men
old men : new men = 40 : 40/3
Multiply by 3:
old men : new men = 120 : 40
Divide by 40:
old men : new men = 3 : 1
Answer: The ratio is 3 : 1
Similar questions