40 workers can make a wall 2om high in 5 hours. How will workers takes to make a wall that is 35m high
Answers
Answered by
0
Answer:
35 meters
Step-by-step explanation:
Assuming the length of the wall is L and if 40 workers can make this 20m-high wall in 5 hours, we can derive that each worker can build 20L/(40*5)=L/10 in one hour.
If the wall is 35m high and assuming the length L is the same, then
35L/(25xL/10)= 35*10/25=14
It will 14 hours for 25 workers to make a wall that is 35 meters high
Answered by
0
Step-by-step explanation:
40 workers can make 20Meter in 5 hours
35M ?
time required for 1m wall =5/20
=0.25hour
time required for 35m wall = 0.25x35
= 8.75 Hour