Math, asked by skmittal5331, 1 year ago

45 men can complete a work in 16 days. six days after they started working, 30 more men joined them. in how many days work will be completed ?

Answers

Answered by mrunalinividya
0
If it takes 45 men 16 days to do the job the whole job takes 45 * 16 = 720 man-days
After four days, they have completed 1/4 of the job. T
hus 3/4 of the job remains; that should take 540 man-days.
With 36 more men working, that brings the total number of men to 81.
The number of days is then found by 540/81 = 6 2/3 days