45 men can do a work in 16 days. After 6 days 30 men were added.
how many day would they
take to complete the work now?
Answers
Answered by
1
Answer:
Let them take x more days to finish the job.
Therefore, 45*16 = (45*6) + (75*x)
i.e. x = 45*10/75
= 6 days.