48 workers can reap a field in 9 days. If the work is to be completed in 6 days, the extra workers required are .?
Select one:
O a. 30
O b. 16
O c. 24
O d. 35
Answers
Answered by
0
Answer:
given-
48 workers,
in 9days
if, 6days
worker?
Step-by-step explanation:
48÷9=5
5×6=30
i guess ans is a) 30
Answered by
3
Given: 48 workers can reap a field in 9 days
To find: The extra number of workers required if the work is to be completed in 6 days
Solution:
Number of workers required if the work is completed in 9 days = 48
Then, number of workers required if the work is completed in 1 day = 48 × 9
Therefore, number of workers required if the work is completed in 6 days
= (48 × 9)/6
= 432/6
= 72
Hence, the extra number of workers required = 72 - 48
= 24
Answer: 24